Upland Community First v. City of Upland CA4/2
Opinion
Opinion
I. INTRODUCTION
In April 2020, defendant and respondent the City of Upland (City) approved the
development of a 201,096 square-foot “warehouse/parcel delivery service building,” to
be located on 50.25 acres near the Cable Airport (the project). As the lead agency for the
project under the California Environmental Quality Act (CEQA; Pub. Res. Code, § 21000
et seq.1), the City passed a resolution adopting a mitigated negative declaration (MND)
for the project (§ 21064.5; 14 Cal. Code Regs. (“CEQA Guidelines”) § 15369.5). In
related resolutions, the City approved an airport land use compatibility request, a site plan
and design review, lot line adjustment, and development agreement for the project. There
is no confirmed tenant for the project.
Plaintiff and appellant Upland Community First (UCF) filed a petition for a writ of
mandate and complaint for declaratory and injunctive relief, asking the superior court to
order the City to set aside the MND and other project approvals. Among other things,
UCF claimed the project violated CEQA (§ 21000 et. seq.) because a fair argument could
be made that the project would have significant impacts on greenhouse gas…