BFS Group, LLC v. ARC.CITY, INC.
Opinion
Trial Court Opinion
O
2 3 4 5 6
United States District Court Central District of California
11 BFS GROUP, LLC, Case № 2:22-cv-03779-ODW (AJRx) Plaintiff, v. ORDER DENYING THIRD PARTY 14 ARC.CITY, INC., PLAINTIFF’S MOTION FOR Defendant. DEFAULT JUDGMENT [102] 16 ARC.CITY, INC., Third Party Plaintiff, v. 19 GONZALEZ AND SONS
CONSTRUCTION INC.,
20 Third Party Defendant. 21 I. INTRODUCTION Following a bench trial, the Court entered Partial Final Judgment against 24 Defendant Arc.City, Inc. and in favor of Plaintiff BFS Group, LLC, finding Arc.City 25 breached its contract with BFS and awarding BFS damages. (Partial Final J., ECF 26 No. 97.) Arc.City now moves as Third Party Plaintiff for entry of default judgment 27 against Third Party Defendant Gonzalez and Sons Construction Inc. (“G&S”), for 28 indemnity and contribution with respect to that judgment. (Third Party Compl. 1 (“TPC”), ECF No. 9; Mot. Default J. (“Motion” or “Mot.”) 2–3, ECF No. 102.) For…