Tonkin Construction Co. v. County of Humboldt

Good Law
188 Cal. App. 3d 828·1987 Cal. App. LEXIS 1282·233 Cal. Rptr. 587
Court of Appeal of CaliforniaJanuary 13, 1987A031452California1,898 words

Opinion

Opinion

Merrill, J.

Respondent Tonkin Construction Company (Tonkin) filed a “complaint for money due” against appellant County of Humboldt (County) for failure to perform certain representations and agreements implied in the parties’ written contract. Following court trial, Tonkin was awarded $27,276.08 in damages against the County. The County appeals, arguing that the record does not support a finding of its liability to Tonkin. We affirm the judgment.

I

In September 1983, the County and the United States Army Corps of Engineers (Corps) undertook to restore the shoreline in a portion of Humboldt Bay. In connection with this objective, the County and the Corps agreed that the County would be responsible for having a seawall built and that the Corps would be responsible for having backfill work performed behind the wall. Such backfill work was necessary for the support and protection of the wall.

The County submitted the contract for the construction of the seawall, entitled the “King Salmon Shore Protection Project, Phase One,” to bidders. Tonkin was the successful bidder on the County’s contract. In turn, the Corps contracted with a dredging company, Osburg, for the performance of the…

Sign in to read the full opinion

Create a free account to read the complete opinion text, citation history, and good-law status for this case.