Ocwd

Golden State Boring & Pipe Jacking, Inc. v. Orange County Water District

Good Law
143 Cal. App. 4th 718·2006 Cal. App. LEXIS 1523·2006 Daily Journal DAR 13261·49 Cal. Rptr. 3d 447·2006 Cal. Daily Op. Serv. 9311
Court of Appeal of CaliforniaSeptember 28, 2006G035795California3,628 words

Opinion

Opinion

Ikola, J.

Colich Construction, LP (Colich), a general contractor, submitted a bid for a public works contract to construct Orange County Water District’s (OCWD) Groundwater Replenishment System Unit II Pipeline Project (the project). Colich’s bid listed Golden State Boring and Pipe Jacking, Inc. (GSB), as a subcontractor. After OCWD awarded the contract to Colich, GSB persistently refused to sign the subcontract requiring it to obtain a performance bond as GSB gratuitously had offered to do in its successful bid for the subcontract. The impasse led Colich to seek OCWD’s approval of its request to substitute GSB out of participation in the project. After an evidentiary hearing, OCWD authorized the substitution, finding under Public Contract Code section 4107, subdivision (a)(1), that GSB’s unjustified intransigence constituted an “unwillingness to execute a written subcontract for the scope of work specified in its sub-bid.” GSB’s petition for writ in mandamus proceedings (Code Civ. Proc., § 1094.5) was denied by the superior court.

On appeal, GSB argues Colich had no right to insist on a performance bond because Colich failed to make a statutory request for bond under section…

Sign in to read the full opinion

Create a free account to read the complete opinion text, citation history, and good-law status for this case.