Hansen Mechanical, Inc. v. Superior Court
Opinion
Opinion
Lillie, J.
Hansen Mechanical, Inc. (Hansen) seeks a petition for writ of mandate to vacate the trial court’s June 14, 1995, order denying its motion for summary adjudication as to the third and fourth causes of action of the cross-complaint of cross-complainant and real party in interest Northridge Equipment Co., Inc. (Northridge), and to enter a new order granting summary adjudication in favor of Hansen. We issued an order to show cause why respondent should not be compelled to grant the relief prayed for in the petition; oral argument has been had thereon. The issue before us is whether Hansen was entitled to summary adjudication of issues as to Northridge’s claims for express indemnity, on the ground that the indemnity provision of the written agreement with Northridge is unenforceable because the agreement was not executed by Northridge within the meaning of Labor Code section 3864.
Factual and Procedural Background
The complaint herein arises out of an April 1990 construction accident involving personal injuries to Sam Martinez, an employee of Hansen. Martinez was operating a mobile scissor lift which allegedly fell into an unguarded hole in a concrete floor at a construction…