S&S Cummins Corp. v. West Bay Builders, Inc.
Opinion
Opinion
McGUINESS, J.
A project to build a public elementary school in Pleasanton suffered substantial delays. After the school was built, the general contractor, West Bay Builders, Inc. (West Bay), refused to release to the electrical subcontractor, S&S Cummins Corporation (Cummins), its share of “retention proceeds” that the school district paid to West Bay following the school’s completion. West Bay justified its refusal to pay Cummins its share of retention proceeds on the ground that Cummins had contributed to delays that caused West Bay to incur damages. Cummins sued for breach of contract, seeking contract damages as well as statutory charges for West Bay’s failure to make prompt payment of the retention proceeds. Following a jury trial, the trial court entered judgment in favor of Cummins for $400,971.
Both West Bay and Cummins appeal from the judgment. West Bay contends the judgment is not supported by substantial evidence, and asserts that the proper application of indemnity and “damages caused by delay” provisions in the subcontract would completely offset Cummins’s damages, compelling a reversal of the judgment. Cummins challenges the trial court’s calculation of statutory prompt…