Law
Bryan Elevator Co. v. Law
Opinion
Lead Opinion
Chipman, J.
In the first count of the complaint plaintiff seeks to recover the sum of sixteen thousand dollars upon a written contract entered into by plaintiff and defendant, January 20, 1905, for the construction and installation of an elevator plant and service by plaintiff for the Monadnock Building, San Francisco. The second count was for necessary repairs to the elevators, elevator equipments, and elevator hatchways in said building of the alleged value of $4,604.33. The third count is for elevator parts and supplies alleged to have 'been sold and delivered to defendant by plaintiff, for which defendant agreed to pay the sum of $2,053.10. Plaintiff had judgment on the first count for the sum of $13,375, with interest from May 1, 1908. The findings and judgment on the second and third counts were in favor of defendant.
Both parties appeal from the judgment. Defendant’s appeal is presented in this record and plaintiff’s appeal on the same transcript is presented in No. 1466. Defendant also appeals from the order denying his motion for a new trial. The cause was tried by the court without a jury. The issues tried may be understood from the findings of facts by the court:
“II.. That…