Contra Costa Construction Co. v. City of Daly

Good Law
1920 Cal. App. LEXIS 289·48 Cal. App. 622·192 P. 178
Court of Appeal of CaliforniaJuly 24, 1920Civ. No. 3333.California1,171 words

Opinion

Lead Opinion

Koford, J.

This is an appeal from a judgment for extra work, in favor of plaintiff and against defendant, a municipal corporation.

The plaintiff and the city of Daly City, a municipal corporation, entered into a written contract for the construction of a water-pipe line for the city’s water supply. The pipe-line was required to be laid, by the contract, plans, and specifications, in Mission road (outside of city boundaries), three and one-half feet below the old curb line of the road. After plaintiff commenced work it was stopped by an injunction not involved here, and before work recommenced it developed, or was discovered for the first time, that the state was undertaking the construction of a section of concrete paved highway along this portion of Mission road. The State Highway Commission, as it is popularly called, asserted and maintained exclusive possession of the road and the right of way, including the strip of land adjoining the pavement where the pipe was to be laid. The city’s engineers thereupon wrote a letter to the Highway Commission asking for a permit on behalf of the city to lay the pipe. This permit was granted, but only on certain conditions as to the manner in which the…

Sign in to read the full opinion

Create a free account to read the complete opinion text, citation history, and good-law status for this case.