Alpert
Dairy Food Store, Inc. v. Alpert
Opinion
Lead Opinion
Bishop, J.
We approve the conclusion reached by the trial court, that the defendants were released from their agreement to lease to plaintiff a portion of a building to be erected, because not the building contemplated but a different one was constructed, the change being due to causes over which the parties had no control. The agreement in question was written by C. H. Gibson, plaintiff’s president, and by him presented to the defendants for their signatures. In so far as it need be before us, it reads:
Whatever Gibson understood, at the time he drew and “accepted” this offer, about the identity of the intending builder, whether it was the defendants, as the offer would indicate, or Baker, as was the fact, he did know that the plan was to erect the building on the land of Baker, and that the source of defendants’ rights in the building would be a lease from Baker. He also knew, as did every party to the transaction, that the city of Pasadena was about to open a street which would cut off a part of the lot upon which the projected building was to be placed. At the time the offer was made and accepted it was quite definitely understood' that the width of the new street would permit a…