Marin Rock Co. v. E. B. & A. L. Stone Co.
Opinion
Lead Opinion
Kerrigan, J.
This is an appeal by defendant corporation from a judgment awarding plaintiff the sum of $598.35 as damages for breach of contract.
From the pleadings it appears that plaintiff entered into a contract with the county of Santa Clara for the construction of a county highway between the towns of Sunnyvale and Cupertino, in said county. It is alleged in the eom plaint that defendant thereafter agreed with plaintiff to sell and deliver to it for a stipulated price all the crushed rock and sand required by plaintiff to perform its contract with the county; that defendant delivered to plaintiff a portion of such rock and sand, but failed and neglected, notwithstanding the demand of plaintiff, to furnish 1,945 tons thereof necessary to the completion of the work; that the plaintiff on account of such default was compelled to and did purchase said amount of rock and sand elsewhere, and paid therefor the sum of $499.31 in excess of the price at which defendant had agreed to sell and deliver the same to plaintiff; that because of said default of defendant plaintiff was damaged in the sum named, with interest thereon. By its answer defendant denied the allegations of the complaint, and,…