Simons Brick Co. v. Eagle Indemnity Co.

Good Law
110 Cal. App. 676·1930 Cal. App. LEXIS 194·294 P. 1075
Court of Appeal of CaliforniaDecember 27, 1930Docket No. 6113.California1,812 words

Opinion

Lead Opinion

Hollzer, J.

The above-entitled actions were tried together and the appeals taken from the respective judgments entered therein are presented upon one and the same record. There is no real dispute as to the facts out of which the suits arose.

In March, 1925, one Callahan, as contractor, entered into an agreement with the Los Angeles city school district for the construction of two school buildings, and in connection therewith furnished a bond executed by the defendant, as surety, conditioned for the payment by the said contractor of all materials, etc., used upon said buildings. Said bond recited in part: “If said principal as contractor . . . fails to pay for any material . . . said surety will pay the sum . . . provided that a verified claim or claims shall be filed as required by an act of the Legislature of the State of California entitled, ‘An Act to secure the payment of the claims of persons employed by contractors upon public works, . . . ’ approved May 10, 1919.”

At the time said bond was executed, the act (Stats. 1919, p. 487), referred to therein required that, before an action could be commenced on the bond, the claimant, within the period allowed by law to file claims of…

Sign in to read the full opinion

Create a free account to read the complete opinion text, citation history, and good-law status for this case.