Norman B. Livermore & Co. v. Guardian Casualty & Guaranty Co.
Opinion
lead Opinion
Conrey, J.
[1] The plaintiff has appealed from the judgment and from an order denying its motion for a new trial. As there is no right of appeal from such a motion, the latter appeal will be dismissed.
[2] On the sixth day of April, 1915, Brashear-Burns Company, a corporation, as contractor, entered into an agreement with the California Highway Commission for the con struetion of a portion of the state highway in Orange County. At the same time, and in connection therewith, the defendant Guardian Casualty & Guaranty Company, as surety, together with said contractor as principal, executed a bond to the state for due payment to be made by the principal for all labor, materials, and supplies furnished for the work of construction under the principal contract. This bond was made pursuant to the provisions of an act approved March 27, 1897. (Stats. 1897, p. 201; amended, Stats. 1911, p. 1422.)
On the fourth day of May, 1915, Brashear-Burns Company entered into a subcontract with W. S. Cook for the performance of work which was a part of the principal contract. Thereupon Cook entered into a contract with one W. F. McDowell whereby it was agreed that McDowell would furnish a certain steam shovel…