Owen
Owen v. Crocker-Huffman Land & Water Co.
Opinion
Lead Opinion
Chipman, J.
The action was commenced to recover damages for land overflowed by an alleged negligently eon structed and maintained canal. The cause was tried by the court with a jury, and, on July 1, 1916, the jury rendered a verdict for plaintiff in the sum of $4,611. Judgment on the verdict was rendered on the same day and was recorded July 3, 1916. On July 7th, defendant duly served and filed its motion for a new trial. The motion came on to be heard, was argued and submitted and the court made the following order: “Motion for new trial having been heretofore argued and submitted, it is ordered that the said motion [be] and tire same is hereby granted, unless plaintiff consents to a reduction of the verdict, as follows, to wit: all in excess of twenty-one hundred fifty-one and 25/100 dollars and costs must be remitted by plaintiff to defendant or a new trial is granted.”
On September 19, 1916, the court made the following order: “It is-ordered that the order heretofore entered, to wit: on Sept. 18th, relative to motion for new trial in the above entitled action, be and the same is hereby changed and modified to correct a mistake arising through inadvertence incorrectly recalling the…