Perazzi
Perazzi v. Doe Estate Co.
Opinion
Lead Opinion
The appeal is from a decree of foreclosure of three contractors' liens against the leasehold interest of appellants in certain premises in San Francisco. The claims of lien sued upon are based upon work performed in the making of alterations and repairs to a portion of the building on said premises, occupied by one J. O. Long as a sublessee of *Page 619 appellants. Mr. Long died on March 31, 1914, while said alterations and repairs were in progress. Upon his death the workmen were withdrawn and all work stopped. The lien claims here involved cover work which was all performed prior to the death of Mr. Long, at his instance and request. [1] Appellants claim that two of these liens were filed prematurely because the contracts upon which they are based had not been completed prior to such filing. The court found that each of the said contracts was completed on March 31, 1914. It is asserted that this finding is unsupported by the evidence, for the reason that the entire alterations and repairs contemplated in the arrangement between Mr. Long and said two respective claimants were not finished at that time. It appears from the evidence that Mr. Long purposed somewhat extensive…
Addendum
The appellants in this action have filed a petition for rehearing, claiming that the court has misinterpreted the contracts of the lien claimants Perazzi and Decker Electrical Construction Company, as set forth in their respective claims of lien; and, further, that, under the interpretation of the contracts adopted by the court, the lien claimants were not original contractors and, therefore, their liens, not having been filed within thirty days, were invalid. Appellants also request a modification of the former opinion as to the prorating of the costs on appeal. In this latter request the respondents have joined in a separate petition, urging, however, a different basis of division of costs. It appears from the notices of lien filed by said Perazzi and Decker Electrical Construction Company that each of said claimants alleged a contract consisting of two items; first, the performance of certain work in changing the location of the barber-shop, for which in each case a definite contract price was agreed upon; and, secondly, for the performance of certain other work, with regard to which no definite *Page 622 price was agreed upon, but each of the claimants was to be paid the…