Cavanagh
Cavanagh v. Keplinger
Opinion
Lead Opinion
Preston, J.
This is an action to enforce a mechanic’s lien for a balance claimed for extras due upon the construction of a building.
The complaint alleges the furnishing of materials and the performance of labor in connection therewith under a contract for the construction by plaintiffs for defendants of a combined residence and garage. It also alleges the completion of the work, the filing of a notice of completion by one of the defendants and the filing thereafter of the claim of lien here sued upon.
The answer admits the filing of the notice of completion, the filing of a lien by plaintiffs and pleads a written contract asserted to be the full and sole measure of the rights of the parties. This written contract was what is known as a guaranteed maximum cost contract with commission attached for the contractor and provided that extras should be calculated upon a cost plus ten per cent basis, said extras to be furnished solely upon order of the architect.
But the evidence abundantly shows that, although the written contract was executed, the parties, in a very large measure, disregarded its provisions, among other things dispensing with the architect therein'provided for and dealing…