Castagnino

Castagnino v. Balletta

Good Law
1889 Cal. LEXIS 842·82 Cal. 250·23 P. 127
Supreme Court of CaliforniaDecember 30, 1889No. 11713California3,528 words

Opinion

Lead Opinion

Thokntox, J.

This action was originally brought to foreclose a mechanic’s lien for $1,395.50 on a block of buildings in the city of San Francisco. The buildings were erected by plaintiff for defendants under a written contract, which provided that plaintiff should furnish all the materials, and do the work according to plans and specifications made by George Bordwell, architect, and receive therefor the sum of $9,800, payable in installments as the work progressed, the last payment to be made “when the houses shall be completed, each in all its parts, and accepted by the architect.” The $1,395.50 consisted of an unpaid balance of the contract price and $375 alleged to be due for extra work and materials. The case was tried, and judgment rendered for plaintiff. An appeal was taken by defendants from the judgment, and an order denying them a new trial, and the judgment and order were reversed on authority of Loup v. Railroad Co., 63 Cal. 97 . The case came on again for trial, and the plaintiff was allowed, over the objections of defendants, to file an amended complaint in indebitatus assumpsit. It contained three counts. The first alleged an indebtedness from defendants to plaintiff of $1,020.50…

Sign in to read the full opinion

Create a free account to read the complete opinion text, citation history, and good-law status for this case.