Webb
Webb v. Kuns
Opinion
Lead Opinion
Temple, J.
This action was brought to foreclose a mechanic’s lien for the sum of $82.50. The appeal is from the judgment and from an order denying a new trial. The general point is that the evidence is insufficient to sustain the finding, and under this an attempt is made to show a variance between the findings and the allegations of the complaint in two respects. As I think no material variance is shown, I will not consider whether the point can be made under the specification.
1. The complaint avers, in accordance with the terms of the contract and the statement in the claim of lien recorded, that plaintiff was to be paid a reasonable sum for any extra work; also that extra work was done. It is found that these allegations are true, and in addition “that the plaintiff performed all the extra work mentioned in the complaint, and fully completed the same, and same was accepted by the defendants on the said eighteenth day of October, 1895, and the defendants agreed to pay therefor the sum of ten dollars.” There is no variance—not even an inconsistency. The finding is not that the work was done under a contract for an agreed price, but to the contrary, and that after it was done defendants…