Transdyn/Cresci JV v. City & County of San Francisco

Good Law
1999 Cal. App. LEXIS 541·72 Cal. App. 4th 746·85 Cal. Rptr. 2d 512·99 Daily Journal DAR 5273·99 Cal. Daily Op. Serv. 4156
Court of Appeal of CaliforniaMay 28, 1999No. A084042California5,236 words

Opinion

Lead Opinion

Ruvolo, J.

I.

Introduction

Appellant Transdyn/Cresci, JV appeals from the trial court’s denial of its petition for writ of mandamus seeking to compel respondent Public Utilities Commission of the City and County of San Francisco (the Commission) to issue appellant a contract to monitor the quality and flow of San Francisco’s water supply. Appellant contends the Commission violated the provisions of the San Francisco Administrative Code when it passed a resolution rescinding the Commission’s earlier contract award to appellant.

We agree and reverse. The action of the General Manager of the Public Utilities Department of the City and County of San Francisco (Department Head) in refusing to sign the contract after the Commission had passed an original resolution awarding the contract to appellant pursuant to competitive bidding laws exceeded the scope of the Department Head’s legal authority, as did the refusal to forward the contract to the Controller of the City and County of San Francisco (Controller) for certification that sufficient funds were available to finance the project. Therefore, the subsequent resolution of the Commission rescinding the contract award to appellant and…

Sign in to read the full opinion

Create a free account to read the complete opinion text, citation history, and good-law status for this case.