Foust

Foust v. San Jose Construction Co.

Good Law
129 Cal. Rptr. 3d 421·198 Cal. App. 4th 181·2011 Cal. App. LEXIS 1050
Court of Appeal of CaliforniaAugust 10, 2011No. H036190California3,164 words

Opinion

Lead Opinion

Premo, J.

Richard Foust appeals from a judgment entered in favor of San Jose Construction Company, Inc. (San Jose Construction), following a three-day court trial on his claim that San Jose Construction breached a written employment contract. Foust argues that the trial court erred in finding that his written employment contract was subsequently modified. In preparing the record on appeal, Foust elected to proceed without a reporter’s transcript and designated only a partial clerk’s transcript.

San Jose Construction, in addition to arguing the merits of the case, has brought a separate motion for sanctions against Foust on the basis that the appeal is frivolous. (Cal. Rules of Court, rule 8.276(a).)

*184 Foust’s showing on appeal is insufficient and we shall affirm the judgment. We also find that the appeal is frivolous and award sanctions against Foust.

I. Factual and Procedural Background

We take our recitation of the facts from the trial court’s statement of decision.

In 1999, San Jose Construction hired Foust as a project manager pursuant to a written employment agreement (the letter agreement). The letter agreement provided for a base salary of $130,000 per year, a…