Toro Enterprises, Inc. v. Pavement Recycling Systems, Inc.
Opinion
Lead Opinion
Gilbert, J.
Here two provisions in a construction contract demonstrate that the greater does not always include the lesser. Subcontractor Pavement Recycling Systems, Inc. (Pavement), appeals from an order denying its motion for attorney’s fees after it prevailed against general contractor Toro Enterprises, Inc. (Toro), on a cross-complaint for contractual indemnity. We reverse because Pavement was entitled to recover its attorney’s fees under the terms of the subcontract.
*956 FACTUAL AND PROCEDURAL BACKGROUND
A general contractor, Toro, undertook a roadway construction project for the City of Oxnard. Toro engaged a subcontractor, Pavement. Near the project, Haffiza Ali was in an auto accident. She sued Toro and others.
Toro cross-complained against Pavement for defense and indemnity, based on a general defense and indemnity provision in their subcontract (section 11). Section 11 provides in relevant part: “To the fullest extent permitted by law, Subcontractor shall defend, indemnify and hold harmless Owner and Contractor and their agents and employees from claims, demands, causes of actions and liabilities of every kind and nature whatsoever arising out of or in connection with…