Northern Plains Resource Council, Inc. v. Surface Transportation Board
Opinion
Opinion
Smith, J.
This case arises out of three applications by the Tongue River Railroad Company, Inc. (TRRC) to build a 130-mile railroad line in Southeastern Montana to haul coal. The Surface Transportation Board (Board), or its predecessor, the Interstate Commerce Commission (ICC), approved each of the three applications (individually, TRRC I, II, and III). Northern Plains Resource Council, Inc. (NPRC), Mark Fix, the City of Forsyth, Native Action, Inc. (Native Action), and United Transportation Union-General Committee of Adjustment (UTU-GCA) (collectively, Petitioners) challenge TRRC II and III. Petitioners challenge the approval of TRRC II and III on a number of environmental and public convenience and necessity grounds.
We hold that the Board failed to take the requisite “hard look” at certain material environmental impacts inherent in TRRC II and III in the manner required by the National Environmental Policy Act (NEPA) prior to approving those applications. We further hold that the Board did not err in its public convenience and necessity analyses, except with respect to its reliance on the viability of TRRC II during the approval of TRRC III. Accordingly, we reverse and remand…