Hans Hoeck v. City of Portland, a Municipal Corporation
Opinion
Opinion
Fletcher, J.
Plaintiff Hans Hoeck appeals from a summary judgment for the defendant City of Portland (the “City”). Hoeck argues on appeal that the district court erred because the demolition of his building constitutes a violation of substantive due process and is a taking under Oregon law. Hoeck also argues that he is entitled to a declaration under 28 U.S.C. § 2201 that he is not liable for demolition costs. We have jurisdiction, 28 U.S.C. § 1291 , and affirm.
FACTS
Hoeck was the owner of the Bridgeport Hotel, a vacant six-story building located in Portland, Oregon. During 1984 and 1985, Hoeck made plans to renovate the Bridgeport and to add four additional stories, converting it into a ten-story office building. After obtaining a financial commitment from a lender and a building permit from the City, Hoeck commenced the renovation project. However, shortly after the project began, the City suspended construction pending a further review of his plan. About six months later, Hoeck was permitted to recommence work. Shortly thereafter, on March 6, 1986, Hoeck’s financing was discontinued due to the insolvency of his lender, and he was never able to obtain replacement financing. Hoeck expended…