American Surety Co. v. United States

Bad Law
136 F.2d 437·1943 U.S. App. LEXIS 4142
United States Court of Appeals for the Ninth CircuitJune 24, 1943No. 10229California459 words

Opinion

Lead Opinion

Healy, J.

One Grogan entered into a contract with the United States for the erection of some buildings at the Government inspection station at Babb-Piegan, Montana. Appellant wrote the bond securing the performance of the contract. Grogan’s time for the completion of the buildings expired June 20, 1933, at which date the work was only partially completed. However, the Government permitted him to continue with it for thirteen months thereafter, or until July 20, 1934, at which time the job was still uncompleted. Grogan was then notified that his right to proceed under the contract was terminated; and the Government thereupon took over the work and finished it.

The contract is the standard form of construction contract. Article 9 thereof, so far as pertinent, reads as follows:

“Delays — Damages.—If the contractor refuses or fails to prosecute the work, or any separable part thereof, with such dili *438 gence as will insure its completion within the time specified in Article 1, or any extension thereof, or fails to complete said work within such time, the Government may, by written notice to the contractor, terminate his right to proceed with the work or such part of the work as to which…

Sign in to read the full opinion

Create a free account to read the complete opinion text, citation history, and good-law status for this case.