Cell-Crete Corp. v. Federal Ins. Co.
Opinion
Opinion
FACTS
A. The Project and the Payment Bond
In November 2013, Granite entered a written contract with the County of
Riverside, agreeing to perform construction services on a project called the Airport
Boulevard (Avenue 56) at Grapefruit Boulevard (Highway 111) and Union Pacific
Railroad Grade Separation project in Thermal, California. In November 2014, Granite
2 and Cell-Crete agreed Cell-Crete would, as part of the project, furnish and install
lightweight concrete and perform related work.
Granite, as principal, executed a payment bond under the terms of Civil Code
section 9554 with Federal as surety for the project. As a condition for acting as surety,
Federal required Granite to agree to defend Federal, indemnify them, and hold them
harmless against any loss, cost, damage, or expense, “including court costs and attorneys’
fees, which it shall at any time incur by reason of its execution and/or delivery of said
bond or bonds or its payment of any claim or liability thereunder.”
B. The Arbitration Proceedings
Disputes arose between Granite and Cell-Crete during construction of the project.